Programme

The following is a list key dates on the project from the commencement of our appointment to its completion:

Feb 2013 - Appointment of Nicholas O'Dywer and AMEC Consulting Engineers
2013/6 - Commencement of initial investigation contracts
2014/6 - Tendering and award of construction contracts
2015 - Commencement of main construction contracts
2016/9 - Completion of scheme

A full breakdown of the project:

Deliverable Duration from Completion Date
Contract Signing 15/02/2013
Project Inception Report March 2014
Third Party Survey Report  March 2014
Design Review Report April 2014
Complete Third Party Contracts Quarter 3 2014

Wastewater Treatment Plant:

Deliverable Duration from Completion Date
Wastewater Treatment Plant DBO Tender Documents submission Quarter 4 2014
Wastewater Treatment Plant DBO Report on Tenders Quarter 1 2015
Wastewater Treatment Plant DBO Contract Award Quarter 2 2015
Wastewater Treatment Plant DBO Contract Completion Quarter 4 2016
Wastewater Treatment Plant DBO Report on Tenders Quarter 1 2015

Southside Networks (Passage West/Monkstown & Carrigaline/Ringaskiddy):

Deliverable Duration from Completion Date
Collection Network Design Quarter 4 2014
Planning Applications for Collection Networks Quarter 2 2015
Collection Network Tender Documents submission Quarter 1 2016
Collection Network Report on Tenders Quarter 2 2016
Collection Network Contract Award Quarter 3 2016
Collection Network Contract Completion Quarter 1 2018

Cobh Network:

Deliverable Duration from Completion Date
Collection Network Design Quarter 1 2016
Planning Applications for Collection Networks Quarter 2 2016
Collection Network Tender Documents submission Quarter 3 2016
Collection Network Report on Tenders Quarter 2 2017
Collection Network Contract Award Quarter 2 2017
Collection Network Contract Completion Quarter 3 2019

 

Key Dates

  • Feb 2013 - Appointment of Nicholas O'Dywer and AMEC Consulting Engineers
  • 2013 - Commencement of initial investigation contracts
  • 2014 - Tendering and award of construction contracts
  • 2015 - Commencement of main construction contracts
  • 2019 - Completion of scheme